Project Costing

Analyze costs across your projects and understand exactly how CrewStat arrives at every number on the Budget Utilization card.

What Counts Toward Project Cost

Project cost has two components:

  1. Expenses — direct costs recorded via the expense module (materials, purchases, reimbursements, etc.)
  2. Labor cost — calculated from attendance records using each worker's cost category rate

How they combine depends on a per-project setting (see Including labor in the budget below).


How Expenses Flow Into Project Cost

Every project has an Actual Cost figure that updates automatically as expenses move through their approval flow:

Expense status Effect on Actual Cost
Draft / Pending Not counted
Approved Added
Paid Counted
Rejected Removed (if previously counted)

You don't need to update this manually — approve or pay an expense, and the project's Actual Cost reflects it immediately.


How Labor Cost Is Calculated

Labor cost is derived from attendance records, using the worker's assigned cost category.

Daily Cost

Attendance status Daily cost
Present (full day) daily_rate
Half Day daily_rate × 0.5
Absent / Leave 0

Overtime (optional)

If overtime is enabled in Settings → HR Setup, overtime hours on an attendance record add to the daily cost:

Overtime cost = (overtime hours ÷ 8) × daily_rate × overtime_multiplier

The overtime multiplier is set on each cost category (typical value: 1.5 for time-and-a-half).

A Simple Example

A Mason with a daily rate of 1,200 works 20 full days and 2 half days in a month, with 4 overtime hours at a 1.5× multiplier:

Full days:     20 × 1,200            = 24,000
Half days:      2 × 1,200 × 0.5      =  1,200
Overtime:      (4 ÷ 8) × 1,200 × 1.5 =    900
─────────────────────────────────────────────
Labor cost                             26,100

Where Rates Come From

Cost categories are configured in Settings → Masters → Cost Categories. Typical setup:

Labour categories

Category Daily Rate
Helper 800
Skilled Worker 1,000
Mason 1,200
Site Supervisor 1,500

Employee categories

Category Daily Rate
Technician 1,500
Junior Engineer 1,800
Senior Engineer 2,500

Each employee / labourer is assigned a cost category in their profile, and the rate that applies is the one effective on the date of the attendance record — so historical costs stay accurate even after you change a category's rate.


Including Labor in the Budget

Every project has a switch that controls whether labor cost counts toward budget utilization:

Setting Total Cost
Include Labour in Budget: Off Expenses only
Include Labour in Budget: On Expenses + Labor cost

Turning It On

  1. Open the project and click Edit
  2. Enable Cost Monitoring
  3. Enable Include Labour in Budget
  4. Save

You can also set a Cost Monitoring Threshold (default 20%) that drives budget alerts when spending outpaces progress.


Budget Utilization

Once total cost is known:

Utilization % = (Total Cost ÷ Estimated Budget) × 100
Remaining     = Estimated Budget − Total Cost

The Budget Utilization card on the project detail page shows:

  • Utilization percentage with a progress bar
  • Total spent (expenses + labor, if enabled)
  • Breakdown — Expenses vs Labor (shown only if Include Labour in Budget is on)
  • Remaining budget

A separate Labor Costs card shows a detailed breakdown:

  • Employee costs
  • Labour costs
  • Overtime cost (if any)
  • Total labor cost

Worked Project Examples

Project A — Villa Construction

Item Value
Estimated Budget 2,000,000
Expenses 0
Labor Cost 144,085
Include Labour in Budget On
Total Cost    = 0 + 144,085       = 144,085
Utilization   = 144,085 / 2,000,000 × 100 = 7.2%
Remaining     = 2,000,000 − 144,085 = 1,855,915

Project B — Office Fit-out

Item Value
Estimated Budget 500,000
Expenses 0
Labor Cost 133,808
Include Labour in Budget On
Total Cost    = 0 + 133,808       = 133,808
Utilization   = 133,808 / 500,000 × 100 = 26.8%
Remaining     = 500,000 − 133,808 = 366,192

Report Contents

The Project Costing report gathers all of the above across your projects and lets you:

  • Compare estimated budget vs actual spend side by side
  • Drill into each project's expenses and labor-cost split
  • Spot projects that are over budget or at risk (spending outpacing progress)
  • Filter by date range, project status, or zone / site

For deeper labor-only analysis, see the Labor Cost report. For expense-only analysis, see Budget vs Actual.